The main objective of the project is to update the landslide early warning system (MAPSREM) based on new data obtained during the disasters in Slovenia in 2023 by:

  1. updating the threshold values for rainfall triggering in the light of climate change

  2. introducing a new variable for the thickness of weathered soil in the landslide probability map

  3. updating the weighting factors of the engineering geological units in the landslide probability map

Project phases and realisation 

WP1 Preparation of input data – Achieved

WP2 Field analysis – Achieved

WP3 Calibration and data analysis and implementation in the MASPREM system – In progress

WP4 Dissemination and project management – In progress